Project Overview
The CTH U Reconstruction Project will improve safety, mobility, and infrastructure within the Village of Biron. The project includes roadway reconstruction, stormwater system upgrades for improved drainage, utility improvements, and recreational trail extension.
Project Updates
Week of October 26th, 2026
Current Work
- American Asphalt placed the first layer of asphalt on Tuesday along North Biron Drive, Center Street, and a portion of Badger Street.
- Crews are working to complete the storm sewer mainline installation by the end of the week.
- Sommers will return this week to begin forming curb.
- Crews will continue coordinating storm sewer, curb, and roadway work as construction progresses.
- An updated construction schedule has been provided, indicating that the remaining Phase 3 work is scheduled to take place next year, from May through June. See the full updated schedule at the link below.
Traffic Impacts
- CTH U remains closed to traffic between South Biron Drive and Beaver Street.
- ND Paper mill traffic is now permitted to cross North Biron Drive at Beaver Street to access the administration parking lot.
- ND Paper traffic will otherwise continue to use the detour route of North Biron Drive to Short Street to Center Street, to Badger Street, to North Biron Drive, and to Beaver Street.
- Head Start traffic will use the detour route of North Biron Drive to Short Street to Center Street to Badger Street to Williams Street access the back of the building for parking as needed.
- All other traffic shall continue using posted detour route out to Huffman Road until otherwise noted.
- Pedestrians are encouraged to use the designated temporary walkway and follow all posted signage.
- Motorists are encouraged to follow all posted signage and traffic control devices.
- Temporary traffic control devices have been installed along North Biron Drive until roadside safety features are restored.
Construction Progress
- The first layer of asphalt has been placed on North Biron Drive, Center Street, and a portion of Badger Street.
- Storm sewer mainline installation is ongoing, with crews anticipating completion by the end of the week.
- Sommers is scheduled to return this week to form curb.
- Construction activities will continue to focus on completing underground utilities and advancing roadway improvements as weather permits.
- The updated schedule identifies May through June of next year as the anticipated timeframe for the remaining Phase 3 work.
Project Schedule
Project Design & Engineering Complete
Roadway Reconstruction and Utility Upgrades (Phase 1) June - August
Roadway Reconstruction and Utility Upgrades (Phase 2) August - November
Roadway Reconstruction and Utility Relocation (Phase 3) May 2027 – June 2027
Paving & Finishing (Phase 1&2) October – November
Paving & Finishing (Phase 3) May 2027 - June 2027
Restoration (Phase 1&2) October - November
Restoration (Phase3) May 2027 - June 2027
Frequently Asked Questions
Phase 1 and 2 of the project is expected to be completed in Fall 2026. Phase 3 of the project is expected to be compelted in early Summer 2027. Construction schedules may change due to weather, site conditions, or other unforeseen circumstances. Please check back regularly for weekly project updates and the latest construction schedule information.
Yes. Temporary restrictions may occur during specific phases of construction, but advance notice will be provided whenever possible.
Mail delivery may be temporarily impacted during construction. A mailbox cluster will be provided on Huffman Road, where residents can pick up their mail during the project. Residents are encouraged to use the mailbox cluster location for mail access while construction activities are occurring. Updates will be provided if there are any changes to mail delivery arrangements.
Updates will be posted weekly, typically every Wednesday. The Village receives the latest construction information during weekly project meetings held each Tuesday at 2:00 PM with the contractor and project team. Following those meetings, project updates will be prepared and posted to this page to keep residents informed of construction progress, upcoming work activities, traffic impacts, and any schedule changes.
This project has four primary points of contact:
- WisDOT Project Manager: Adam Osypowski
Phone: (715) 459-1670
Email: adam.osypowski@dot.wi.gov - Contract Manager: Skyler DeBoer, Earth, Inc.
Phone: (715) 305-1151
Email: skyler.earth@tds.net - Project Engineer: Tim Schoenherr
Phone: (715) 323-0311
Email: tim.schoenherr@questllc.biz - Wood County Highway Department: Roland Hawk
Phone: (715) 421-8875
Email: roland.hawk@woodcountywi.gov
The WisDOT Project Manager oversees the project on behalf of the Wisconsin Department of Transportation and serves as the primary project representative. The Contract Manager coordinates day-to-day construction activities and field operations. The Project Engineer is available to answer technical and design-related questions regarding the project. The Wood County Highway Commissioner provides oversight and coordination on behalf of Wood County Highway Department.